Hardware Commissioning: Requests for Controls
 

Injection system - back burner for the moment.

See also SACEC

Software


1. Update the Fixed Displays (FD) (configure with the mode?). Display at least 1 and preferably all the FDs on the web.
2. Provide a Page 1 / quadrant, definitely on the web
3. An electronic logbook (that does not replace the MTF and is inspired on the facility provided by Felix for String 2). This must be visible on the web.
4. Applications to continuously monitor the hardware (monitoring is for visual inspection, fixed displays do not provide sufficient detail, specialists applications may be inappropriate)
5. Programs for vacuum system, cryogenics, powering, quench protection and interlocks. (could be specialists programs if available)
6. A global Post Mortem system with analysis and display facilities specified by the hardware commissioning team.
7. Some software with an interface to the Access System may be required.
8. Powering Application specifically tailored for hardware commissioning
9. Global logging
10. Global alarms


Requirements